COMPLETING A SCHOOL COMMUNITY
Loganville Elementary School is part of a planned campus on a 98-acre site. Loganville Middle was the first part of the school community, with the elementary school following in 2016.
This compact, single-story design offers natural light to the classrooms through corridor skylights and transoms. The main entrance displays a two-story barrel roof with high clerestory windows. The circulation desk in the media center is capped with a clerestory lighted turret. The commons area features a stage, allowing it to serve as a multipurpose room. Maintenance is accomplished through interior utility corridors, which provide access without disturbing classrooms. Between the middle school and the elementary school is a 200-seat amphitheater with a covered stage.
Project Specifics:
4889 BAY CREEK CHURCH ROAD,
LOGANVILLE, GA 30052
BUILDING AREA: 114,615 SF
SITE AREA: 98 acres
DESIGN CONTRACT AWARD: $17,850,560
FINAL COST: $17,778,699
CONSTRUCTION DELIVERY METHOD: CM@Risk
FINAL CONSTRUCTION DURATION: 14 months
SUBSTANTIAL COMPLETION: July 8, 2016
WALTON COUNTY BOE: Mr. Greg Yevick,
Director of Facilities
CONTRACTOR: Carroll Daniel Construction Co.